The Protecteur class (formerly known as the Queenston class) of naval auxiliaries for the Royal Canadian Navy (RCN) began as the Joint Support Ship Project, a Government of Canada procurement project for the RCN that is part of the National Shipbuilding Procurement Strategy. It will see the RCN acquire two multi-role vessels to replace the earlier auxiliary oiler replenishment vessels.
The project has suffered from considerable delays. Originally announced in 2004, a contract for the construction of these ships was planned to be signed in 2009, with the first vessel available for operational service in 2012. In 2010, the federal government incorporated the project into the National Shipbuilding Strategy.
On 2 June 2013, ThyssenKrupp Marine Systems Canada's replenishment ship was selected. The Canadian vessels will be a variant of the Berlin class, built at Seaspan's yard in North Vancouver, British Columbia.
Initial construction work began in 2018, but a formal contract for the construction of both ships was only signed in June 2020.
In order to speed construction of the Protecteur-class naval auxiliaries, the delivery of the first of the new class of polar icebreakers, the , will be delayed until at least 2030.
Class name
On 25 October 2013, the Minister of National Defence named the JSS the Queenston class with two ships named, HMCS Queenston and Châteauguay. Their namesakes were battles of the War of 1812, Queenston Heights and Châteauguay. A name was also chosen for a possible third ship in the class, HMCS Crysler's Farm, named after the Battle of Crysler's Farm. The option for the third vessel was dropped due to budget constraints.
On 12 September 2017, the Canadian government renamed the vessels, taking the names of the ships of the class that they are to replace. Queenston became Protecteur and Châteauguay became Preserver. According to Vice-Admiral Ron Lloyd, commander of the RCN, this was due to the ties both serving and former navy personnel had with the names.
Purpose
The Joint Support Ship Project consists of two multi-role vessels that will replace the former underway replenishment capability of the earlier Protecteur-class auxiliary vessel, as well as provide basic sealift for the Canadian Army, support to forces ashore, and command facilities for a Canadian Forces "joint force" or "naval task group".
The Joint Support Ship Project should not be confused with the Amphibious Assault Ship Project, which was a proposed separate procurement project that never advanced beyond the concept stage.
Proposed ship capabilities
, the Joint Support Ship Project envisioned several multi-role vessels capable of supporting the Royal Canadian Navy's warships at sea, as well as providing strategic sealift and some airlift for naval task groups or army operations. The vessels were envisaged as having a multi-purpose covered deck with the ability to carry up to 10,000 tonnes of ship fuel, 1,300 tonnes of aviation fuel, 1,100 tonnes of ammunition as well as 1,000–1,500 lane metres of deck space for carrying vehicles and containerized cargo. The vessels were also to have hospital facilities as well as a large helicopter deck with two landing spots, hangar space for four helicopters, and a roll-on/roll-off deck for vehicles onto a dock. The actual capabilities have been listed as being able to carry 64 twenty-foot equivalent units of shipping containers, which can be used to store food, water, vehicles, and other specialized equipment to support land or sea-based operations, including humanitarian aid or disaster relief. Additionally, these containers can house special mission fit cargo, such as mobile hospitals and portable communication centers, which could be offloaded or airlifted ashore. hold up to 6,875 tons of F76 marine fuel, 1,037 tons of F44 aviation fuel, an on board hospital with surgical and dental facilities.
Particulars of the Berlin-class design
The Berlin-class design ultimately selected incorporated somewhat modified components:
Ability to transport of fuel, of water, of ammunition, of food, of dry stores and 32 containers. Ship fitted with replenishment-at-sea (RAS) systems and accommodates up to two helicopters. The loading and offloading of cargo is carried out by two 24-ton cranes. The modular hospital of the Berlin class has 45 beds for general patients and four for intensive care (including hospital ward).
The Canadian variant of the Berlin class may incorporate additional modifications from the original design.