The Tide is a light rail line in Norfolk, Virginia, United States, owned and operated by Hampton Roads Transit (HRT). It connects Eastern Virginia Medical School, downtown Norfolk, Norfolk State University, and Newtown Road. Service began on August 19, 2011, making it the first light rail system in Virginia. Fares match local bus fares and the line accepts HRT's GO Passes. Trains generally run every 15 minutes, increasing to every 10 minutes during peak periods and every 30 minutes during early mornings and late evenings. In , the system had a ridership of , or about per weekday as of .

History

In the late 1980s, the Tidewater Transportation District Commission (TTDC) began producing studies that would examine the feasibility of expanding transit corridors between Norfolk and its neighboring cities of Chesapeake, Portsmouth, Suffolk, and Virginia Beach; these included a study for the cost effectiveness of restoring passenger rail service in 1986 and a rail systems analysis in 1991. Four years later, TTDC pursued a Major Investment Study and in 1997, identified a locally preferred alternative for an east–west light rail line between downtown Norfolk and the Virginia Beach oceanfront. The alignment would have run along an exclusive double-track right-of-way that followed the Norfolk Southern Railway and contained 13 stations. In 1999, the Virginia Beach City Council asked its residents in a referendum whether it should adopt a local ordinance to help develop and finance the light rail project. On November 2, Virginia Beach residents voted against the referendum, 56percent to 44percent.

The Tide (light rail network)

After Virginia Beach pulled out of a proposal that would have seen the construction of a light rail line connecting downtown Norfolk with the Virginia Beach oceanfront in 1999, Norfolk began developing a network that would be constructed entirely within its city limits.

The Tide (light rail network)

Beginning in 2000, HRT and federal transit officials worked to create a plan that would attract federal funding. On September 22, 2006, the Federal Transit Administration announced that the proposal met federal criteria for design, and would receive funding for a final design. On October 1, 2007, the FTA signed the agreement to appropriate $128 million for the construction of the network. The remainder of the project will be divided three ways, with the city of Norfolk contributing $33 million, the Commonwealth of Virginia contributing $31.9 million, and $39.2 million being contributed from other federal sources.

The Tide (light rail network)

Officials announced in June 2007 that the system would be called The Tide, a name that beat out other proposed names, including Bay Runner, First Rail, Dash, Bay Breeze, Sail and Shore Line.

Construction problems

The line had been planned to open in January 2010, but cost overruns, extended testing of trains, and electronic signage required three delays.

In January 2010, HRT's executive director, Michael Townes, was pressured by the board of directors and ultimately agreed to step down after the project overshot its budget by $100 million and missed by one year its operational deadline. A majority of the board members cited poor management and communication on his part. He was to serve at full pay and benefits helping with a transition and continue to seek additional funding until September 2010, after which the board agreed to a severance package of full pay and benefits for another full year. As an interim measure, the board hired former VDOT Commissioner Philip Shucet for 1 year effective February 1, 2010 at the rate of $40,000 per month to lead the agency, with a mandate to restore financial integrity and communication pending selection of a new executive director.

In May 2010 elections, voters ousted Norfolk city councilman Randy Wright, a long-time incumbent, HRT board member, and light rail supporter. His opponent, also an advocate of light rail, cited the waste and delays under Towne's administration. Another HRT board member, Paige Washington, also lost a reelection bid in Hampton. News media sources reported that "Three million dollars [of HRT funds designated for projects on the Virginia Peninsula] were diverted to Norfolk to [help] pay for its light rail cost overrun".

Opening

On June 21, 2011, HRTs announced the line would open on August 19 initially with demonstration rides followed by regular service beginning on August 22. Due to high ridership during the initial demonstration period, estimated at over 46,000 riders, the demonstration period was extended, with regular service to begin on August 28.

On September 21, 2011, Hampton Roads Transit announced the introduction of online ticketing and onboard WiFi to The Tide.