The Tawa Flat deviation is a double-track section of the Kapiti Line just north of Wellington, New Zealand with two tunnels; the southernmost section of the North Island Main Trunk railway (NIMT) between Wellington and Auckland. It was built to bypass a limited capacity single track section of the original Wellington and Manawatu Railway (WMR) line which ascended from Wellington to Johnsonville and then descended to Tawa Flat. The original name of Tawa Flat was changed to Tawa in 1959.

When opened to passenger trains in June 1937, the deviation reduced the travel time from Wellington to Porirua by 15 minutes, to 27 minutes rather than 43 to 48 minutes. By 2016, the time from Wellington to Porirua had further reduced to 21 minutes for stopping trains, despite extra stops at Redwood, Linden, and Kenepuru which each add 48 seconds to the travel time, and to 17 minutes for non-stopping trains.

Tawa Flat deviation

The deviation

The original line from Wellington, constructed by the WMR, wound up the south side of the Ngaio Gorge with steep grades, tight curves, and tunnels with curves in them, to Ngaio, Khandallah, and Johnsonville before descending through difficult hilly country to Tawa Flat.

Tawa Flat deviation

The new line split from the existing line at Thorndon, where the old line began its ascent to cross the Hutt Road toward Wadestown and Johnsonville. It shared tracks with the Wairarapa Line to the new Distant Junction, where Aotea Quay joins the Hutt Road, where it split from but followed the Wairarapa Line along the waterfront to Kaiwharawhara before climbing a new bank to enter the southern portal of the new No. 1 tunnel (1,238 m). From the northern portal of the new No. 2 tunnel (4,323 m) at Glenside it followed the floor of the Tawa valley down to Tawa Flat where it joined the existing line south of McLellan Street, near the boundary of present-day Tawa College and Tawa Intermediate.

Tawa Flat deviation

The deviation was the first stage of the electrification of the NIMT railway from Wellington to Paekākāriki, and duplication to Pukerua Bay. It saved , lowered the summit level from south of Raroa to at the north portal of No 2 tunnel, and reduced the maximum gradient from 1 in 36 (on the initial climb out of Wellington) and then 1 in 40 (to Ngaio and Khandallah) to a maximum of 1 in 110 in No 1 tunnel and 1 in 122 in No 2 tunnel. Previously the maximum load out of Wellington for a locomotive was 175 tons, and some trains were banked and then re-formed at Johnsonville. The new NZR Ka class steam locomotives could haul 600 rather than 280 tons, although further north between Plimmerton to Paekākāriki they were limited to 490 tons. Hence electrification extended to Paekākāriki, so including the climb up the bank between Plimmerton and Pukerua Bay. The grade in the opposite direction was 1 in 100 on the climb south from Tawa to Takapau Road and the north portal of No 2 tunnel.

Planning

In 1914 the NZR General Manager E. H. Hiley told parliament that the Johnsonville-Wellington section of the NIMT was approaching capacity, and in 1915 NZR district engineer A. Kock and the Public Works Department submitted a report which was deferred until after World War I.

In 1923 various options were investigated including tunnels direct from Koro Koro to Linden and Petone to Tawa Flat (though this option would interfere with Hutt traffic and require a sea wall to protect the line along the waterfront). Five options for the deviation were considered. They were: two alternative routes with tunnels from Takapu Road to the Korokoro Stream near Petone, a tunnel from Takapu Road to a point a little southwest of the Horokiwi Stream on the harbour edge, an alternative northern portal for the northern of the two tunnels constructed (Tawa No.2 tunnel), and the chosen route.

The total cost of the deviation was estimated at £1,409,000. Rock excavated from the tunnels was to be used for harbour reclamation to provide access to the first tunnel and to enlarge the rail yard in Wellington.

Construction

The deviation of about 7 miles (11.3 km) as the Wellington-New Plymouth Line (Wellington - Tawa Flat Deviation) was authorised by the Railways Authorisation Act, 1924. The deviation was running generally to the eastward of the existing Wellington - New Plymouth railway. As built there were two long tunnels; Tawa No. 1 ( with a 1 in 110 gradient) and Tawa No. 2 ( with a 1 in 122 gradient). Tawa No. 2 tunnel, which remains the longest double track tunnel in New Zealand, passes under Newlands and comes out at Glenside, en route to Tawa.