The Kalpasar Project or the Gulf of Khambhat Development Project envisages building a 30 km dam across the Gulf of Khambat in India for establishing a huge fresh water coastal reservoir for irrigation, drinking and industrial purposes. The project with 30 km sea dam will have the capacity to store 10 billion cubic meters fresh water, equating to 25% of Gujarat’s average annual rainwater flow, from the rivers like Narmada, Mahi, Dhadhar, Sabarmati, Limbdi-Bhagovo, and two other minor rivers. A 10 lane road link will also be set up over the dam, greatly reducing the distance between Saurashtra and South Gujarat. The project, which will create world's largest freshwater lake in marine environment, will cost INR90,000 crore or US$12.75 billion (2015-16 estimates with 8% annual inflation) excluding the cost of tidal power plant. Project entails construction of the main "Kalpasar dam" across Gulf of Khambat and another Bhadbhut barrage on Narmada river, as well as a canal connecting the two.
Spending began in earnest in 2004, and by 2018 INR 250 crore has been spent on various feasibility studies and surveys. By July 2019, 25 of the 43 feasibility studies for the ecological, environmental, social and financial impact, etc were complete; 8 more were underway; remaining 10 surveys will take 3 to 5 years to complete i.e. by 2021-23. Detailed Project Report (DPR) was intended to be completed by the end of 2018. The project, if found feasible, will take at least 20 years (by 2035-38) to complete including 3 to 5 years pre-construction feasibility studies which are presently underway, and further 12 to 15 years of construction thereafter which has not commenced yet. As of 2018, no environmental or other clearances have been obtained for the Kalpasar dam. Meanwhile the construction of the Bhadbhut barrage, which is a smaller component of the project, commenced in 2020.
More than 30,000 MCM of water from Narmada river alone flows out annually into the sea due to the lack of storage capacity and dams, thus experts have been calling for a review of Gujarat's Water Policy to expedite the Kalpasar project.
Background
Etymology
Kalpasar means a lake that fulfills all the wishes (कल्प+सर). The construction of the word is similar to कल्पवृक्ष, the Hindu mythological ‘Kalpa Vriksha’ (Devanagari: कल्पवृक्ष) – wishing tree.
History
The Gulf of Khambhat was identified as a promising site for tidal power generation by UNDP Expert, Mr. Eric Wilson in the year 1975. Successive governments were then presented in details the possibility of a project, aptly named Kalpasar Project by its visionary Dr. Anil Kane, who conceptualised it in 80s as a feasible project. In 1988–89 a reconnaissance report was prepared for the dam across the Gulf of Khambhat. The report concluded that, assuming sound foundation conditions, the closure of the Gulf was technically feasible. Studies are still going on and the length of the proposed dam is reduced and the tidal power component is dropped. The cost of project is estimated at 85,000 crore as of 2022. It is reported that the project may take 20 years to complete if found feasible and approved.
Project details
Objectives
Kalpasar aims at the creation of a fresh water coastal reservoir in the Gulf of Khambhat by the construction of a dam connecting the east and west bank of the Gulf. In the reservoir the runoff from Sabarmati, Mahi, Dhadar and Narmada will be stored, together with the waters from the Saurashtra rivers discharging into the Gulf of Khambhat. The stored waters are to be used for irrigation, domestic and industrial water requirements in the Saurashtra region. Kalpasar is considered the evident solution for solving on the short as well as on the long term the threatening drinking and irrigation water problems in Saurashtra.
Once the Gulf is closed, water levels within the reservoir can be controlled while the tidal fluctuation outside the reservoir continues and, hence, can be harnessed for the generation of tidal energy.
In addition to fresh water storage and tidal power generation, Kalpasar also aims at land reclamation, transportation improvements and fisheries development. In accordance with this project, a mega fresh water reservoir will be constructed on the upstream side of the dam by impounding the surplus waters of numerous rivers.
This project, will resolve four vital problems of the State of Gujarat which are water, electrical power, road-rail transport and development of ports.
Scope and cost
Abandoned original plan and scope
The original plan envisaged a larger dam along with a tidal power plant.