The Tasmanian Main Line Company (T.M.L.) was a privately owned railway company that existed in Tasmania from 1872 to 1890. The company were the first operators of rail services between Hobart and Launceston, where it connected with the Launceston and Western Railway (L.W.R.).

Initial proposals

The idea of a railway linking Hobart with Launceston went back at least as far as 1855 when a move was put forward by a member of the State Upper House to put $2,000 aside in the estimates for a survey, which in turn led in 1856 to the Surveyor-General being asked to make a preliminary survey. Actual beginnings towards constructing a railway occurred in 1863, when Parliament allocated $10,000 for surveys of the route to the north. One proposed route by Messrs. Doyne, Major and Willett of the Launceston & Western Railway, was similar to the future line built by T.M.L. but had an easier grade, was twenty kilometres longer and would enter Hobart via Park Street instead of along the Derwent foreshore. Other routes suggested going through Green Ponds and Oatlands as more desirable, and another deviated to Antill Ponds, proceeded along the Macquarie and Isis Valleys to Longford thereby joining the L.W.R. to Launceston.

Tasmanian Main Line Company

Until the construction of the L.W.R. in the north, Hobartians had been indifferent to the idea of a railway. Henceforth, they pressured the government to build their own railway line, some suggesting to Devonport, with a branch going to Launceston.

Tasmanian Main Line Company

In 1868, a Royal Commission was set up to enquire into the cost of constructing a railway from the capital to Launceston. In respect of gauge, the Commission concluded that "the requisite conditions of comfort, speed, construction and cost have been found to combine most perfectly in the 4 feet 8½ inches gauge".

Tasmanian Main Line Company

Once the report of the Royal Commission was printed in the Hobart newspaper, The Mercury, no time was lost before money was voted by Parliament for a proper survey to be made. Through the winter of 1869, the Railway and Progressive Association called public meetings and lobbied politicians. During August, The Mercury almost daily called for Government action.

On 11 September 1869, the Government announced that it proposed to ignore certain of the recommendations of the Royal Commission and parts of the Survey Engineers' Report. The Government was ready to subsidise any company to the extent of £300,000. The Attorney-General introduced a Bill into Parliament to give effect to this proposition. After some hesitations, the Bill passed all stages. It was now a question of negotiating with some company or firm of railway promoters. The necessary capital and professional skill was to be found in England. It was emphasised that the gauge was to be and that the railway was to be completed by the last day of 1874.

In May 1870, the Government was advised that there was an English firm prepared to form a company which could operate with a capital of £1,000,000. What it required was a stronger guarantee from the Government and suggested 6% on £850,000 for 30 years.

Company formed

A considerable amount of offers and counter-offers ensued, and the promoters of the Tasmanian Main Line Railway Company initially perceived having a gauge such as that of the L.W.R., however the outcome being an acceptance between the T.M.L.R. and the Government to construct a railway of from Hobart to Evandale. British-born engineer John C. Climie was appointed engineer, having previously been engaged to assess the site of the Table Cape lighthouse, as well as the Emu Bay Railway in 1878, and designed several bridges in Victoria.

The railway was intended to run right into Launceston, but the Launceston and Western Railway had already built a broad gauge line along that route. It was agreed that a third rail would be laid within the broad gauge tracks. The Government guaranteed a return of 5 percent on A£650,000 for 30 years.

Construction

There was an inauspicious start. Excessive rains during August and September 1872, held up surveying. Then it was found that the route originally proposed was "impracticable". Mr J.W Reeve, engineer and managing partner in Tasmania for the London contractors Clarke, Punchard & Reeve, arrived in Hobart in June 1872. Reeve and his engineering staff believed they could complete the railway, telegraph and all works by late 1874. In mid-1872, two 0-6-0T engines built by Fox and Walker of Bristol, arrived in Launceston on the barque Westbury. They were used by the contractors as construction engines.