Inland Rail, also known as Inland Railway and previously Australian Inland Railway Expressway, is a railway line under construction in Australia. Once complete, it will connect the ports of Melbourne and Brisbane along a new route west of the mountainous Great Dividing Range, bypassing the busy Sydney metropolitan area and allowing for the use of double-stacked freight trains. The route will also connect to the Sydney–Perth rail corridor, reducing journey times between Brisbane, Adelaide and Perth.

Construction of the line is divided into 13 projects, with of new track to be built and of existing track to be upgraded.

Inland Rail

History

Early proposals

In 1889, a proposed standard gauge and partly mixed gauge line from Brisbane via Rosewood, Warwick and Wallangarra shortened the distance between Brisbane and Sydney by .

Inland Rail

In the 20th century, several proposals were made for an inland railway route connecting the east coast of Australia. In 1915, Prime Minister Andrew Fisher proposed a "strategic railway" connecting the South Australian city of Port Augusta to Brisbane, with connections to the New South Wales railway network, at an estimated cost of A£6,500,000. In 1979, TNT founder Ken Thomas proposed a route connecting Brisbane to Melbourne via Wallangarra, Orange and Albury, with possible connections to Adelaide and Perth.

Inland Rail

Later proposals

In 1995, Queensland Rail detailed a $1.289 billion (equivalent to $ billion in ) proposal for an inland railway corridor connecting Brisbane and Melbourne. New dual gauge track would follow the existing narrow gauge Main Line to , the Western railway line to Wyreema and the Millmerran railway line to its terminus at Millmerran, with new track connecting to the Boggabilla railway line south of the New South Wales–Queensland border.

The route would then have continued along the Mungindi railway line until Bellata, with a new line connecting the Coonamble railway line via Wee Waa before once again following existing track: the Main Western railway line to ; the Parkes–Narromine railway line to ; the Stockinbingal–Parkes railway line to ; the Lake Cargelligo railway line to ; the Main Southern railway line to ; and the North East railway line to Melbourne. A maximum line speed of would be in place for the corridor, with an additional $189 million (equivalent to $ million in ) upgrade to existing track allowing for speeds of up to in sections.

In 1996, the Bureau of Transport and Communications Economics (BTCE) released a working paper assessing the proposal. It found a new route would save ten hours journey time on the existing coastal route via Sydney, reducing the operating cost for operators from $23.16/tonne to $17.56/tonne, but would facilitate only a small increase in grain production.

In September 2005, the federal Department of Transport and Regional Services commissioned a feasibility study into a Brisbane–Melbourne railway link, outlining four possible 'sub-corridors' between and Brisbane. In May 2008, the newly elected Rudd government allocated $15 million to the Australian Rail Track Corporation (ARTC) to develop a route alignment following the Far Western sub-corridor as detailed in the 2006 study. The corporation's preliminary analysis was released in May 2009, which showed that the cheapest version of the inland railway would cost $2.8 billion to build and would allow freight to be moved from Melbourne to Brisbane in just over 27 hours. Despite this, the analysis also found that, if operational by 2020, the project's costs would outweigh any economic benefits by up to $1.1 billion.

The ARTC's final report was released in July 2010. The report recommended a route from Junee to Melbourne via following the North East railway line, with the route from to Brisbane to build along a new corridor through the Toowoomba range. The report forecast a delivery cost of $3.688 billion, with track duplication works between Junee and Melbourne and capacity for double-stacked freight trains between Melbourne and Parkes already budgeted by the ARTC.

Approval and funding

The Gillard government announced forward estimates of $300 million in the 2011 federal budget commencing 2014, with the Coalition committing to the funding following the election of the Abbott government in 2013. A further $594 million was allocated to ARTC by the Turnbull government in the 2016 federal budget to purchase land for the project, with an additional $8.4 billion in funding over seven years announced in the subsequent 2017 budget.