The Puerto Rico Electric Power Authority (PREPA; Spanish: LUMA, AEE) was an electric power company owned by the Commonwealth of Puerto Rico responsible for electricity generation, power distribution, and power transmission on the island. PREPA was the only entity authorized to conduct such business in Puerto Rico, making it a government monopoly, until on January 22, 2018, former governor of Puerto Rico, Ricardo Rossello, announced that all assets of the company will be sold in a general privatization of PREPA.

The authority was ruled by a board of directors appointed by the governor with the advice and consent of the Senate. After 2014, PREPA was subject to the Puerto Rico Energy Commission, another government agency whose board of directors was also appointed by the governor.

Puerto Rico Electric Power Authority

Hurricane Maria in September 2017 destroyed PREPA's distribution network, creating a blackout in all parts of the island.

Puerto Rico Electric Power Authority

History

PREPA was originally named the Puerto Rico Water Resources Authority (PRWRA) which was created by Act. 83 of May 2, 1941, during the governorship of Rexford G. Tugwell. Government-owned, PRWRA unified diverse regional and local electric power companies into one unified electric grid.

Puerto Rico Electric Power Authority

Maintenance budget

Over the years the budget for maintenance, such as clearing trees near power lines, has diminished: in 2007 it was $251 million and in 2014 it was $202 million.

Outages

Throughout its history, PREPA has suffered several outages that have left regions or the entire island of Puerto Rico without power.

In August 2012 14,000 residents where left without power following the passing of tropical storm Isaac.

One of these islandwide outages occurred on September 20, 2016, due to a fire at one of PREPA's plants—Central Aguirre. All of Puerto Rico was without power for three days.

On occasion, entire sectors are reportedly left without power when an animal, such as a cat or an iguana, causes damage to the system.

In September 2021 demand for electricity exceeded supply, after mechanical and maintenance problems affected various power plants, resulting in four days of consecutive rolling blackouts. Central Aguirre and Palo Seco faced problems with the removal of seaweed since the filters to prevent the accumulation of such needed replacement. The power outages resulted in the cancellation of classes at the Pontifical Catholic University of Puerto Rico and a student protest at the University of Puerto Rico.

Hurricanes Irma and Maria

At the first days of September 2017, the eye of Hurricane Irma passed north of the island. The strong winds left 1 million residents without power. Power had been restored to 980,000 people by September 20, when Hurricane Maria struck, leaving nearly the entire island without power. Two weeks later, power had been restored to about 10% of customers. Full restoration took months, and many Puerto Ricans bought generators. Electric companies in unaffected areas ordinarily make contracts for speedy assistance to those hit by disaster, but in this case negotiations took weeks.

The initial $300 million contract for power restoration was given to Whitefish Energy, a Montana company which had only two employees on the day the hurricane struck. The award was controversial on those and other grounds, and was cancelled on October 29. By December 2017, the Army Corps of Engineers had other contractors in place, along with crews brought in through mutual aid agreements with utilities such as Con Edison.

Six weeks after Hurricane Maria, 30% of customers had been restored. After two months, almost half had been restored.

On January 6, 2018, representatives of FEMA, the U.S. Army Corps of Engineers and their armed security details entered a Palo Seco warehouse owned by PREPA to obtain and distribute a massive store of spare parts were needed to restore grid power. PREPA has been accused of hoarding the materials and hence delaying the restoration of power. The equipment has since been distributed.

In January 2018, it had been predicted that generation would reach 95% by the following month, and 100% of customers would be restored by June 2018.

On April 18, 2018, an accident at a transmission line knocked out the electrical grid of Puerto Rico. All the island lost power. The following afternoon, PREPA announced that service had been restored to 97% of customers, the same percentage as before this blackout. 40,000 customers were still out of service due to the hurricane seven months earlier.