Trams in Liège, Belgium, date back to horsecars which were replaced by electric trams starting in 1893. Trams in Liège were abandoned by the end of 1967. However, trams would make a comeback in the form of the Liège tramway (French: tramway de Liège) possibly in 2025.

The Liège tramway is a light-rail line under construction to connect the communities of Sclessin (fr) and Coronmeuse (fr) along the Meuse passing by Liège-Guillemins railway station and Place Saint-Lambert within the city. The line will also have a branch to Bressoux (fr) where the line's maintenance and storage center is located. , the line is expected to be put into service in January 2025. The line will be operated in a public–private partnership, whereby the private partner Tram'Ardent maintains the trams and infrastructure and the publicly owned TEC operates the trams.

Trams in Liège

History

Early years

The first electric tram service in Liège, which was also the first in Belgium, opened to the public on 9 August 1893, connecting the northern Coronmeuse district (fr) with Herstal, to the east of the city. Only of the line actually ran in the city centre. On 22 October 1896, the two principal horse-powered tramlines were converted to electric power, forming an electric tramline that crossed the city centre. In 1897, a line was added connecting Chênée (then considered a separate town) with the city centre, and Angleur received a tram connection in 1905. A fourth line was also installed that year for the World's Fair in Liège.

Trams in Liège

An aspect of tram operations in Liège was the large number of competing operators. By the start of the 20th century, there had been some consolidation of the businesses involved, but in 1905, there were still six different organisations operating trams in the city, some in public ownership and some privately owned. In addition to the electric trams, the lines were also used by steam trams at this time. It was only in 1927 that the Liège tram network was "unified".

Trams in Liège

Decline and closure

The tram collection at the contains numerous tramcars that predate the Second World War and some that predate the First World War, which were decommissioned only in the mid 1960s. Evidence is sparse of any trams having been added to the city's fleet after the 1930s, although most of the tramcars were subject to at least one major overhaul or rebuild exercise during their service. In view of the challenging topography (at least by Belgian standards) of Liège, and the visible absence of investment, the last tram services were withdrawn in November 1967.

Metro aborted

Major investment in a Liège underground Metro system was envisaged and construction eventually began towards the end of the 1970s. A tunnel was started, but the Metro never saw the light of day. The tunnel section that was completed enjoys enduring notoriety as one of Belgium's white elephants. It is used for storage.

Return

In 2008, regional political leaders generally agreed on reintroducing trams to Liège in order to address the city's traffic saturation issues, particularly in its low lying central parts by the river Meuse. Extensive investigation and public consultation followed, before the first line's route was fixed in October 2011. The regional government of Wallonia gave the final go-ahead at the end of 2011, although at that stage, it was stated that further discussion remained necessary on project funding. In the end, the decision was taken to proceed on the basis of a public–private partnership, inspired by agreements used for recent investments for the London Underground.

Revised plan

The line was originally planned to be long, comprising a length from Seraing to Herstal and a further for a short branch connection to Bressoux (fr). The plan was revised to build the line in stages initially only from Sclessin (fr) to Coronmeuse, serving 21 tram stops, covering approximately . The projected cost of €315 million compares with an estimated cost of €484 million for building the entire line at once. The decision not to proceed at once with the full line drew criticism.

Third Eurostat rejection

By August 2013, tenders for the construction had been received from three consortia. That was narrowed down to two on 3 April 2014, when the remaining contenders were invited to submit their final bids for 15 September 2014. The final decision was announced on 10 December 2014, in favour of the so-called "Mobiliège" consortium (ALSTOM – BAM PPP PGGM – DG Infra).