Arrow is a commuter rail service in San Bernardino County, California, United States. Opened on October 24, 2022, the line runs from the San Bernardino Transit Center in Downtown San Bernardino in the west to the University of Redlands in Redlands in the east.

The line was planned and constructed by the San Bernardino County Transportation Authority as the Redlands Passenger Rail Project and is operated under contract by Metrolink, which integrates Arrow into its commuter rail system, making it the only line in the entire Metrolink system to be entirely in San Bernardino County and also became the second line not to serve Los Angeles Union Station nor cross the Los Angeles River since the opening of the Inland Empire–Orange County Line in October 1995. This is the first and only Metrolink line to utilize completely different rolling stock than the rest of the system.

Arrow (rail service)

Operation

Route

The route uses a former Atchison, Topeka and Santa Fe Railway line. While mostly a single track line, of double track were constructed in the middle of the route to allow vehicles to pass each other. Low-volume freight service by BNSF Railway uses the route during overnight hours when Arrow service is not running for a few customers located on the portion of the line just west of San Bernardino–Tippecanoe station.

Arrow (rail service)

Hours and frequency

Most trip schedules are coordinated to allow relatively short connection times with San Bernardino Line trains at San Bernardino Transit Center for trips to and from Los Angeles. One trip early in the morning and two later in the evening will be added once Arrow receives permission to implement a quiet zone and stop sounding train horns at level crossings along the route.

Arrow (rail service)

Stations

From west to east, the line starts at the San Bernardino Transit Center (also called station), where passengers can transfer to several local and regional bus routes, Metrolink trains and the sbX bus rapid transit line, the line then makes stops at station, crosses under Interstate 10 and enters Redlands reaching the station, after that trains enter central Redlands serving station, built alongside the historic Redlands Santa Fe Depot, before reaching its final stop, station at the University of Redlands.

Rolling stock

FLIRT DMUs built by Stadler Rail were selected for service on the line under a $31.4 million contract. An additional FLIRT utilizing hydrogen fuel cell energy storage has been developed by Stadler for use on the line, with a planned introduction in 2024.

History

Previous rail service in Redlands included the Pacific Electric "Red Car" trolley system and the Atchison, Topeka and Santa Fe Railway. The PE's San Bernardino Line served Redlands from Los Angeles by way of its Eastern District, which opened in 1905 and was abandoned in 1937. Extant infrastructure includes the PE right of way, the ATSF's Redlands depot and the Redlands Trolley Barn.

Proposals for a restored passenger rail connection between San Bernardino and Redlands were made as early as the 1990s, with the service originally projected to start in 1995. This date has progressively been delayed to 2013, 2015, and 2018. The project was then known as the Redlands Passenger Rail Project.

By 2011, the estimated cost of construction was between $130 million and $150 million. The first contract for the project was awarded on November 2, 2011, by San Bernardino Associated Governments (SANBAG) to HDR, Inc. for engineering and environmental services. The contract was an amendment to an existing contract for HDR to work on a separate project in the region, the extension of the San Bernardino Line to a new terminus at the San Bernardino Transit Center.

In September 2010, the SANBAG considered options that included Metrolink train service, other types of electrified or diesel trains, and buses. In April 2011, SANBAG announced that it had settled on conventional heavy rail equipment for the service. This would be provided by refurbished ex-Metrolink rolling stock operating on 30-minute peak period headways and hourly off-peak headways. While SANBAG preferred electrified light rail, its $268.1 million cost was over the $250 million limit for the federal Small Starts transit grants that would have been used. The estimated cost of heavy rail service was $198.6 million, which could be paid for using federal transportation grants that were based on population and sales tax revenues.