This case illustrates the integration of federal and state jurisdictions in licensing water power projects under the Federal Power Act. The petitioner is the First Iowa Hydro-Electric Cooperative, a cooperative association organized under the laws of Iowa with power to generate, distribute and sell electric energy. On January 29, 1940, pursuant to § 23(b) of the Federal Power Act, it filed with the Federal Power Commission a declaration of intention to construct and operate a dam, reservoir and hydro-electric power plant on the Cedar River, near Moscow, Iowa.

On April 2, 1941, it also filed with the Commission an application for a license, under the Federal Power Act, to construct an enlarged project essentially like the one it now wishes to build. The cost of the enlarged project is estimated at $14,600,000. It calls for an 8,300 foot earthen dam on he Cedar River near Moscow, an 11,000 acre reservoir at that point and an eight mile diversion canal to a power plant to be built near Muscatine on the Mississippi. The canal will create two other reservoirs totaling 2,000 acres. It is alleged that the three reservoirs incidentally will provide needed recreational facilities. The power plant will have four turbo-generating units with a total capacity of 50,000 kw., operating with an average head of 101 feet of water provided by the fall from the canal to the Mississippi. Water will be pumped from the Mississippi up to the head bays of the power intake dam at the plant to meet possible shortages in supply. The tailrace will extend for a mile along the shore of the Mississippi to a point below Dam 16 on that River. Transmission lines will connect the project with a source of steam standby electric current at Davenport, Iowa, 24 miles up the Mississippi. The plant is expected to produce 200,000,000 kwh. of marketable power per year, of which 151,000,000 kwh. will be firm energy in an average year. Interchange of energy is proposed with the Moline-Rock Island Manufacturing Company near Davenport and the project is suggested as an alternative to the addition of a 50,000 kw. unit to the plant of that company. The power will be available especially to non-profit rural electrification cooperative associations and to cities and towns in 35 or more nearby counties.

First Iowa Hydro-Electric Cooperative v. Federal Power Commission/Opinion of the Court

The Cedar River rises in Minnesota and flows 270 miles southeasterly through Iowa to Moscow which is 10 miles west of the Mississippi. From there it flows south-westerly 29 miles to Columbus Junction where it joins the Iowa River and Returns southeasterly 28 miles to the Mississippi. The proposed diversion will take all but about 25 c.f.s. of water from the Cedar River at Moscow. This will correspondingly reduce the flow in the Iowa River while the diverted water will enter the Mississippi at Muscatine, about 20 miles above its present point of entry at the mouth of the Iowa River. There are no cities or towns on the Cedar River between Moscow and Columbus Junction and the record indicates that the petitioner has options upon 98% of the riparian rights on the Cedar River in that area. At petitioner's request, this application was treated as a supplement to its then pending declaration of intention to construct the smaller project.

First Iowa Hydro-Electric Cooperative v. Federal Power Commission/Opinion of the Court

On June 3, 1941, the Commission made the following findings:

First Iowa Hydro-Electric Cooperative v. Federal Power Commission/Opinion of the Court

(1) That the Cedar and Iowa Rivers are navigable waters of the United States;

'(2) That the diversion of water from the Cedar River by means of the diversion canal as set forth above would have a direct and substantial effect upon the flow and stage of the Iowa River and hence would affect the navigable capacity of that river;

'(3) That the alternate withholding of water in the reservoir and canal during periods of shut-down of the power plant and the release of water at substantial rates of flow during periods of operation of the power plant, as set forth above, would cause extreme fluctuations in the flow of the Mississippi River at Muscatine, Iowa, and would substantially affect the navigable capacity of that river;

'(4) That the interests of interstate commerce would be affected by construction of the project as described in the declaration of intention as supplemented;

'(5) That the two small islands * * * (in the Cedar River) are public lands of the United States and will be partly or wholly flooded by the reservoir of the proposed project and will be occupied by the project.

'(6) That a license for the construction porposed above is required under the provisions of the Federal Power Act.' 2 Fed. Power Comm.Rep., 958.