AMOUNT OF MATERIAL MOVED BY ONE MAN WITH A PICK AND SHOVEL

(From H. P. Gillette) ────────────────────────────────────────┬────────────────────────────── Material │ Cubic Yard per hour ────────────────────────────────────────┼────────────────────────────── Hardpan │ 0.33 Common earth │ 0.8 to 1.2 Stiff clay │ 0.85 Clay │ 1.00 Sand │ 1.25 Sandy soil │ 0.8 to 1.2 Clayey earth │ 1.3 Sandy soil (frozen) │ 0.75 ────────────────────────────────────────┴──────────────────────────────

Sewerage and Sewage Treatment — Part 180

The opening of the trench may be facilitated by breaking ground with a plow. In hard ground or on paved roads it may be necessary to cut through the surface crust with a hammer and drill, although in some cases a plow can be used successfully. Frozen ground can be thawed by building fires along the line of the trench, or greater economy may be achieved by placing steam pipes along the surface with perforations about every 18 inches and either boxing them on the top and sides or burying them in the frozen earth with a covering of sand. Another arrangement is to blow steam into a line of bottomless boxes in which each box is about 8 feet long. Holes are left in the top of the boxes into which the pipe is shoved, and after its withdrawal the holes are covered. Blasting of frozen earth is sometimes successful but cannot be resorted to in built up districts where it is unsafe unless properly controlled. Once the frost crust is broken through it can be attacked from below and frequently broken down by undermining.

Sewerage and Sewage Treatment — Part 180

A laborer cannot dig and raise the earth much more than to the height of his head, and preferably not quite so high, without tiring quickly. After the trench has passed a depth of 4 feet he cannot throw the earth clear of the trench. An additional laborer is needed then at the surface to throw the earth back. He should shovel the earth from a board platform placed at the edge of the trench as a protection to the bank. When the trench passes the 6–foot depth a staging is put in about 4 feet from the top on which the lowest laborer piles his materials. It is then passed up to the surface by a second laborer on the staging, and a third laborer on the surface throws the material back clear of the trench. Stagings are put in about every 5 or 6 feet for the full depth of the trench.

Sewerage and Sewage Treatment — Part 180